Assigning Resources in a Schedule
In Primavera P6, after you create the Project Plan, you may need to assign resources
to make the resource plan.
After the resource is created in the RBS (Resource Breakdown Structure) in Primavera,
you can assign resources to activities inside a project.
Let’s say you have a project plan from start to finish, one like this one:
You need to start assigning resources to it. In order to do that you can go either these
two options:
Option 1: go to each of the activities and assign them manually
1.Go to Activities>Activity Detail>Resources:
Option 2: assign massively Resources for a group of activities
Note: Milestone activities can’t have resources assigned, just as Primary Resources.